CITRACADO MEDICAL OFFICE BUILDING
Location: Escondido, California
Owner: Physician Management Group, Inc., San Diego, CA Architect: Freeman White, San Diego, CA, David Wolfe General Contractor: Pacific Building Group, San Diego, CA CAA Project Manager: Graham C. Anderson/Christina Castro Project Budget: $13,053,341. |
Scope of Services: Total management of all
aspects of design, permitting, bidding and construction administration
from project inception through completion. CAA was engaged in
April 2004 as the owner’s Construction Manager to assist in the development of
a 48,300 GSF, two-story medical office building. The project comprised the building shell/core
and associated site development on an approximate 2.6 acre site. CAA’s role included the management of tenant
improvements for approximately 50% of the available shell space. The remainder of the tenant improvements will
be completed as dictated by tenant leasing.
The shell portion of this project was completed in January 2007 on
schedule and on budget.